Empire’s group of installers has done more acoustical installations than anyone worldwide. With more than 20 years experience they provide a professional installation or technical guidance for the customer that chooses to do their own install. Various installation applications include:

  • Ground Mounted
  • Barrier Mounted
  • Wall Mounted
  • Fencing
  • Blast Deflectors
  • Roof Tops
      • Sandwich
      • Parapet Attachments
      • Stub up column and grade beams

Installing Panels:

  • The pallets will be brought to the installation area from the storage. This will be done using a fork lift. Alternately a number of panels will be shifted to the installation area by truck and or a trailer to ensure that less time is spent in going back and forth between the storage and installation site.
  • The panels weigh 6 lbs per sq ft and for a panel of 14 ft length the maximum weight of the panel is 84 lbs.
  • The panel is then lifted, using crane truck, by slings secured at the center of the panel.
  • The panel is lifted and lowered into place between 2 pre set beams. The panels are supported by the flange of the beam and the retaining angle that is loosely bolted to the beam.
  • The worker after hand setting the panel into place reaches behind the panel to tighten the bolts thereby clamping the retention angles tightly to the back tray of the panel.
  • The panels are installed in 2’ increments (vertically) to allow the worker to reach behind the panels to tighten all bolts.
  • Once the first pass of 2 ft is complete from end to end, the steps are repeated to complete the wall installation.